Home
>
Festival Info > Maps and Travel > 2010 Street Closures
2010 Street Closures
STREET CLOSURES
Note: All closures commence at 12:01 AM on the first day of the closure,
and end at 6:00 AM on the final day of the closure, unless indicated
otherwise. Closures current as of
February 10, 2010.
Monday, April
5, 12:01 AM to 6:00 AM Monday, April 12.
· Main Street from 2nd Street to 9th Street (Cross streets remain open)
·
8th Street from Houston Street to Main
Street: One curb lane on the South side and the
parking curb cut will be closed from 12:01 am Monday April 5 until 12:01 AM
Wednesday, April 7. (Full street
closure 12:01 AM Wednesday April 7 to 6:00 AM Monday April 12).
·
Houston Street parking curb cuts, East side between 3rd
Street and 4th Street to include bagging of
parking meters: 12:01 AM Monday, April 5 to 6:00 AM Monday, April 12.
Tuesday, April 6, 12:01 AM
to 6:00 AM Monday, April 12
· Main Street from Weatherford Street to 2nd Street: 12:01 AM Tuesday, April 6 to 6:00 AM
Monday, April 12.
·
6th Street from Houston Street to Commerce Street: Two outside lanes (north
& south curb lanes) will be closed 9:00 AM Tuesday, April 6 until 6:00 PM
Friday, April 9. (Full street
closure 6:00 PM on Friday, April 9 to Monday, April 12 at 6:00 AM). Note: Two (2) center lanes will remain
open to traffic until 6:00 PM Thursday and Friday. Access to Hotel parking garage entrance and access to Parking
Garage (between Main St. and Houston St.) will be maintained.
·
7th Street from Houston Street to Commerce Street: Two outside lanes (north & south curb lanes) will be closed 9:00 AM
Tuesday, April 6 until 6:00 PM Friday, April 9. (Full street closure 6:00 PM on Friday, April 9 to Monday,
April 12 at 6:00 AM). Note: Two
(2) center lanes will remain open to traffic until 6:00 PM Thursday and
Friday.
· 9th Street from
Houston Street to Commerce Street: 12:01 AM
Tuesday, April 6 to 6:00 AM Monday, April 12.
·
4th Street parking lane south side,
Houston Street to Throckmorton Street: 12:01 AM Tuesday, April 6 to 6:00 AM Monday, April 12. This lane will be used for
porta-lets for the event.
Wednesday
April 7, 12:01 AM to 6:00 AM Monday, April 12
· 1st Street from Houston Street to Commerce Street: 12:01 AM Wednesday April 7 to 6:00 AM
Monday, April 12. Access to
Renaissance Worthington Parking Garage will be maintained.
·
2nd Street from Houston Street to
Commerce Street: 12:01 AM Wednesday April 7 to 6:00 AM Monday, April
12. Access to the
Renaissance Worthington portico will be maintained. Street closure will
not be initiated until after rush hour on Thursday and Friday.
·
3rd
Street from Houston Street to Commerce Street:
12:01 AM Wednesday, April 7 to 6:00 AM Monday, April 12. Access to Haltom’s Jewelry loading zone
will be provided by barricade pass.
·
4th Street from Houston Street to Commerce Street: 12:01 AM Wednesday, April 7 to 6:00
AM Monday, April 12. Two (2) North
lanes will be open during rush hour traffic (6:00 AM – 9:00 AM), Wednesday,
April 7, Thursday, April 8 and Friday, April 9. 4th Street will close entirely (all lanes) for
the weekend at 9:00 AM on Friday, April 9 – Monday, April 12. Access
to Parking Garage will be maintained.
·
5th Street from Houston Street to Commerce Street: 12:01 AM Wednesday, April 7 to 6:00 AM Monday, April 12. Two (2) center lanes will be open all
day on Wednesday, April 7 and during rush hour traffic (4:00 PM – 6:00 PM)
Thursday, April 8 – Friday, April 9, 2010. 5th Street will close entirely (all lanes) for
the weekend at 6:00 PM on Friday, April 9 – Monday, April 12, 2010.
·
5th Street parking lane, north side: Bagging of parking meters
from Houston Street to Throckmorton Street: 12:01 AM Wednesday, April 7 to 6:00
AM Monday, April 12. This lane will be used for merchant back-up parking
(restaurants & hotel).
·
8th
Street from Houston Street to Commerce Street:
12:01 AM Wednesday, April 7 to 6:00 AM Monday, April 12. Access to Hilton Hotel will be
maintained. Restaurant valet
parking service will be moved to Houston Street.
·
Close parking lane (curb lane) and bagging of
parking meters Commerce Street (West side of street) and Houston Street
(Eastside of street) between 1st Street and 9th Streets to be used as a Golf Cart lane: 12:01 AM Wednesday, April 7 to 6:00 AM
Monday, April 12. This lane will be used for golf carts to move through the
event in a safe manner and not impede traffic or block sidewalks.
·
Close parking and bagging of parking meters
Weatherford Street (South- side) between Main Street and Commerce Street: 12:01 AM Wednesday, April 7 to 6:00 AM Monday, April 12. Parking to be used for permit-only
event staff and support.
·
Close Houston Street parking curb cuts, East side
of street, and bagging of parking meters from 2nd Street to 9th
Street: 12:01 AM Wednesday, April 7 (changed
from Thursday) to 6:00 AM Monday, April 12. These parking spaces will be used
for permit-only service vehicles.
Thursday,
April 8 12:01 AM to 6:00 PM Sunday, April 11
·
Close first traffic lane westside of Commerce Street from 1st
Street and 9th Streets to be used as a Golf Cart
lane: 12:01 AM Thursday, April 8
to 6:00 AM Monday, April 12. This lane will be used for golf carts to move
through the event in a safe manner and not impede traffic or block sidewalks.